Kumasi International Airport 77% Complete; Set To Be Completed In June 2022

Spread the love

The President of the Republic, Nana Addo Dankwa Akufo-Addo, has inspected ongoing work on construction of the Kumasi International Airport, which, according to the contractor, is currently 77% complete, and is expected to be completed in June 2022.

 

President Akufo-Addo visited the site of the construction on Friday, 1st October 2021, when he commenced his 4-day working visit to the Ashanti Region, as part of his annual working visits to all the Regions of the country.

 

 

 

It will be recalled that on 6th June 2018, the President cut the sod for the commencement of work on Phase Two of the Kumasi Airport Project, where he indicated that “the expansion of this airport is a critical part of government’s vision to expand the frontiers of the aviation industry in the country, and to realise the dream of making Ghana an aviation hub in West Africa.”

Inspecting work on the site, the President was told that the terminal building was 88% complete, the road network 93% complete, the Apron 89% complete, with the air traffic control and rescue and firefighting services 53% complete.

 

 

May be an image of text that says 'ghanaa ports kc ARUP DEVELOPMENT CONTRACTA KUMASI INTERNATIONALAIRPORT PHASE II/III TERMINAL BUILDING 88% ROAD ROADNETWORK RUNWAY EXTE NSION STRIPPING APRON 93% ATC/RFFS 40% 89% L 53% 77% GENERAL GENERALLAYOUT'

 

 

 

 

 

 

 

The scope of work include the extension of existing runway pavement from 1,981 metres to 2,320 metres, the construction of a new taxi link and apron, two new apron parking stands, aeronautical ground lighting systems, the design and building of a terminal with the capacity to handle eight hundred thousand passengers per annum, an 11 MW substation, as well the provision of new bulk utility (electricity, water, sewage treatment system, internet etc.) services, independent of the existing utility services for the existing airport facilities.

 

 

 

 

 

No photo description available.

 

 

 

 

 

No photo description available.

 

 

 

 

 

 

Phase three (3) of the project involves the construction of the air traffic control building, a fire building station, as well as the expansion of the existing runway pavement. The construction of the fuel farm is to be funded by GOIL.

 

 

 

May be an image of indoor

 

 

 

 

 

 

 

 

 

May be an image of indoor

 

 

With the project being constructed by Messrs. Contracta Construction UK Limited, the total project sum is €124.9 million, with financing from Santander, Deutche Bank, and UKEF.

 

 

 

May be an image of outdoors

 

 

 

 

 

 

 

May be an image of 6 people, people standing and text that says 'POLICE GHANA TCE'

 

 

President Akufo-Addo expressed satisfaction with the progress of work undertaken so far, and charged the Ministry of Transport as well as the Contractor to ensure that the October 2022 deadline for completion is met.

 

 

 

 

 

 

 

Source:  presidency.gov.gh

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Disclaimer: MyGhanaMedia is not responsible for this report and its content.There are four types of content published on MyGhanaMedia daily: curated content; syndicated content; user-generated content; and original content.

 

 

 

 

 

 

 

 

 

 


Send your news stories to myghanamedia@gmail.com and Chat with us via WhatsApp on +233 200818719

 

 

About Adwenpa-Hene

we publish on Entertainment, Sports, Politics, Lifestyle, and Technology. You can also follow Us on : YouTube Channel - My Ghana Media TV, Facebook - MyghanaMedia TV , Twitter - @MyGhanamedia2 & Instagram - My Ghana Media TV. Email Address: myghanamedia@gmail.com Contact Us: 0200818719

Check Also

Ghana: Today’s Newspaper Headlines; Friday, November 22, 2024.

Spread the love Below  are the major news headlines captured on the front pages of …

x