Works Begin On New KATH Maternity And Children’s Block Demolition Plans Get Underway

Spread the love

Work has started on the construction of a five-storey structure to replace the long-stalled Maternal and Children’s block at the Komfo Anokye Teaching Hospital in Kumasi.

Excavation of the project site is ongoing as contractors prepare to demolish the existing structure.

After years of neglect, the existing building failed a structural integrity test.

The new building will be constructed with the €138 million budget already secured for the project.

The bed capacity will, however, be reduced by 250.

Head of Architecture at the Ministry of Health, Richard Vandapuije briefed journalists on the scope of the proposed new structure.

“Within three years the contractor promises to finish this structure including demolishing of the existing one. Discussions will be held with KATH to finalise the detailed internal layout”, he said.

Meanwhile, management of Komfo Anokye Teaching Hospital is in support of the demolition of the existing structure.

See also  Pressure Mounts On Gov't To Scrap SIM Re-registration Deadline [Audio]

Chief Executive Officer, Dr. Oheneba Owusu Danso, outlined that “the new structure being developed should not affect the duration or expected completion of the project.”

“It should add extra value to what would have been derived from the existing one”

He added that, ” it should be scallable to meet additional space so urgently required by the hospital. The basis of the change is based on independently verifiable facts and this is why the KATH management fully endorses the view of the contractors and Ministry.”

The Ministry of Health says the long-stalled Maternity and Children’s block fails to meet the minimum standard required by building regulations.

See also  Election 2020: Families Of Casualties In Techiman South Violence To Get 4-Bedroom House

A tour of the building revealed concrete over beams falling off by rubbing with a finger, with steel enforcement weakened.

Iron rods were rusty, a situation contractors blame on extreme weather conditions.

Technically, contractors reveals columns and walls have weak quality of C7/C9 MPa, which is beneath standard of C20/C25.

Concrete beams achieved a quality of C10/C12. It also failed other tests conducted on the building.

While taking journalists on a tour of the facility, is Project Manager for Archito Consult, consultants to the contractor Emmanuel Asabre showed support systems holding the pillars in place to prevent the building from possible collapse.

See also  Doctors At Komfo Anokye Teaching Hospital Declares Indefinite Strike Effective March 13

Construction firm, Contracta says construction of the new building and demolition of the old structure will progress concurrently.
Various governments since 1976 have worked on the project at various stages with any hope of conclusion.

A JoyNews documentary by Seth Kwame Boateng titled “Next to Die”, highlighting challenges at mothers, compelled the government to source funding to complete the project.

Source: Myjoyonline

Disclaimer: MyGhanaMedia is not responsible for this report and its content.There are four types of content published on MyGhanaMedia daily: curated content; syndicated content; user-generated content; and original content.

Send your news stories to myghanamedia@gmail.com and Chat with us via WhatsApp on +233 200818719

About Adwenpa-Hene

we publish on Entertainment, Sports, Politics, Lifestyle, and Technology. You can also follow Us on : YouTube Channel - My Ghana Media TV, Facebook - MyghanaMedia TV , Twitter - @MyGhanamedia2 & Instagram - My Ghana Media TV. Email Address: myghanamedia@gmail.com Contact Us: 0200818719

Check Also

NCA Approves Starlink’s Satellite Broadband Application

Spread the love The National Communications Authority (NCA) has approved Space X Starlink GH LTD, …